LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Updated On
 
Sl.NoWorkcodeTal_NameSub TypeSectorCategoryWORK NAMEAGENCY NAMEPlan App DATEAllocationAdm APP DateADM AmtWO AmtEXPStages of workStatus Type NameLast Modified
1 HK151713117KalaburagiInstitutionalUniversityGENERALConstn of Boys Hostel at Central University, Kalaburagi KRIDL-123/07/2016 196.82 23/07/2016196.820.00157.46foundation work U/PUnder Progress11/3/2017 11:53:42 AM
2 KLB152623230AlandInfrastructurewater supplyGeneralProviding addl 250 KVA transformer @ Nimbarga MVS jackwell in Aland taluka RWS23/12/2016 7.41 23/12/20167.417.330.00ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress2/24/2018 10:26:56 AM
3 KLB153113197ChincholiInfrastructureNemmadi UruGeneralNemmadi Uru Chincholi: Town HallKRIDL-226/08/2016 199.80 26/08/2016199.800.0080.00Lintel Laid Under Progress4/8/2018 12:32:50 PM
4 KLB153113198ChincholiInfrastructureNemmadi UruGeneralNemmadi Uru Chincholi: Shopping MallKRIDL-218/01/2016 199.00 18/01/2016199.000.00180.00Nearing CompletionUnder Progress4/8/2018 12:33:06 PM
5 KLB153113199ChincholiInfrastructureNemmadi UruGeneralRCC drain with footpath from Gandhi Chowk to Tandur cross Chandapur in Chincholi TownKRIDL-226/08/2016 142.55 17/12/2016122.330.0045.00C.C. Drain Work U/P.Under Progress5/18/2018 1:08:07 PM
6 klb153123284ChincholiInfrastructureWater SupplyGENERALInstallation of WPP plant in Ranapur village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00 ಸೆಲ್ಟರ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:50:27 PM
7 klb153123285ChincholiInfrastructureWater SupplyGENERALInstallation of WPP plant in Potangal village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:51:13 PM
8 klb153123286ChincholiInfrastructureWater SupplyGENERALInstallation of WPP plant in Mukaramba village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:51:42 PM
9 KLB153123318ChincholiInfrastructureWater SupplyGENERALInstallation of WPP plant in Halchera village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೆಸಮೆಂಟ್ ಮುಗಿದಿದೆ Under Progress5/21/2018 12:49:43 PM
10 KLB154123202ChittapurInstitutionalTransportGeneralConst of bus shelter at Nagavi temple in chittapurNK09/03/2017 10.00 09/03/201710.000.006.59Borewell drilling completed & lintel levelUnder Progress6/21/2018 12:23:13 PM
11 KLB154123204ChittapurInstitutionalTransportGeneralConst of bus shelter at near court in chittapur townNK09/03/2017 10.00 09/03/201710.000.006.41Borewell drilling completed & lintel levelUnder Progress6/21/2018 12:24:42 PM
12 KLB154123205ChittapurInstitutionalTransportGeneralConst of bus shelter at lodging cross in chittapur townNK09/03/2017 10.00 09/03/201710.000.006.59Borewell drilling completed & plinth work u/pUnder Progress6/21/2018 12:25:52 PM
13 KLB154123206ChittapurInstitutionalTransportGeneralconst of bus shelter near KRSTC bus depot in chittapur townNK09/03/2017 10.00 09/03/201710.000.006.68Borewell drilling completed & plinth work completedUnder Progress6/21/2018 12:26:31 PM
14 klb154123289ChittapurInfrastructureWater SupplyGENERALInstallation of WPP plant in Gundgurthi village under Jalamrith RWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:52:55 PM
15 klb154123290ChittapurInfrastructureWater SupplyGENERALInstallation of WPP plant in Sugur.K village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress5/21/2018 12:53:30 PM
16 KLB155123207JewargiInfrastructureNemmadi UruGeneralNemmadi Uru Jewargi: Town HallPWD KLB17/09/2016 196.65 17/09/2016196.65188.0171.98First Floor lintel levelUnder Progress4/13/2018 6:33:36 PM
17 KLB155123208JewargiInfrastructureNemmadi UruGeneralNemmadi Uru Jewargi: Shopping MallKRIDL-102/08/2016 199.21 02/08/2016199.210.00120.00ಪ್ಲಾಸ್ಟರೀಂಗ್ ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress4/8/2018 1:03:26 PM
18 KLB155123209JewargiInfrastructureNemmadi UruGeneralElectirfication work at ward no 38 and installation of Controlling point in JewargiTMC JEWARGI12/01/2016 31.15 01/03/201727.9618.603.67Work Under ProgressUnder Progress4/13/2018 2:48:07 PM
19 klb155123293JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Kurnalli village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00 ಸೆಲ್ಟರ್ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:54:15 PM
20 klb155123294JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Varchanalli village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೆಸಮೆಂಟ್ ಮುಗಿದಿರುತ್ತದೆUnder Progress5/21/2018 12:54:41 PM
21 klb155123295JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Gogihal village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:55:10 PM
22 klb155123296JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Revnoor village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೆಸಮೆಂಟ್ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:56:34 PM
23 klb155123297JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Mallabad village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:57:11 PM
24 KLB155123298JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Kattisangavi village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:57:44 PM
25 KLB155123299JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Briyal.k village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಮುಗಿದಿದೆUnder Progress6/6/2018 10:56:55 AM
26 KLB155123300JewargiInfrastructureWater SupplyGENERALInstallation of WPP plant in Kallur.B village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಮುಗಿದಿದೆUnder Progress5/21/2018 12:58:35 PM
27 KLB156123074SedamInstitutionalWater supplyGeneralProvision of RO Plants in Govt. LPS School premises of Indira ngar Fasaladi tanda of Sedam talukRWS24/09/2015 1.50 23/11/20151.501.480.00ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress5/8/2018 1:15:36 PM
28 KLB156123075SedamInstitutionalWater supplyGeneralProvision of RO Plants in Govt. High School premises of Neelahalli village of Sedam talukRWS24/09/2015 1.50 19/11/20151.501.480.00ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress5/8/2018 1:16:32 PM
29 KLB156123211SedamInfrastructureNemmadi UruGeneralNemmadi Uru Sedam: Town HallKRIDL-201/09/2016 199.94 01/09/2016199.940.00100.00Ground Floor Roof Laid Plastring U/PUnder Progress5/8/2018 11:17:07 AM
30 KLB156123212SedamInfrastructureNemmadi UruGeneralNemmadi Uru Sedam: Shopping MallKRIDL-217/09/2016 199.94 17/09/2016199.940.0090.00Plastering Work U/P Under Progress5/18/2018 1:08:51 PM
31 klb156123310SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Devnoor village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 1:02:10 PM
32 klb156123311SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Rudrawar village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress6/2/2018 1:19:09 PM
33 klb156123312SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Boothpur village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 1:03:32 PM
34 KLB156123313SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Turnoor (Kalkamba ) village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೇಸಮೆಂಟ್ ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress6/2/2018 1:19:53 PM
35 KLB156123314SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Hayyal village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 1:04:36 PM
36 KLB156123315SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Bijanalli village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 1:05:13 PM
37 KLB156123316SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Bilkal village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೆಸಮೆಂಟ್ ಮುಗಿದಿರುತ್ತದೆUnder Progress5/21/2018 1:05:39 PM
38 KLB156123317SedamInfrastructureWater SupplyGENERALInstallation of WPP plant in Madakal village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಬೇಸಮೆಂಟ್ ಕೆಲಸ ಪ್ರಗತಿಯಲ್ಲಿದೆUnder Progress6/2/2018 1:20:36 PM
39 KLB157113170KalaburagiInstitutionalPark GeneralProviding & fixing of street light at Rajiv gandi theme park kalaburagiNK23/12/2015 47.78 23/12/201547.780.000.00WorK under progressUnder Progress6/21/2018 1:10:03 PM
40 KLB157113172KalaburagiInstitutionalPark Generalconstn of Chain link fencing for Public exhibition ground Kotnoor D Park, KalaburagiNK26/08/2016 34.10 17/02/201733.120.005.77Front side column castedUnder Progress6/21/2018 1:12:22 PM
41 KLB157113188AfzalpurInstitutionalSportsGeneralConstruction of pavilion building at Stadium in Afzalpur town Dist Kalaburagi part IKRIDL-218/01/2016 154.10 18/01/2016154.10154.1070.00Coloum Up to Lintel Level Under Progress3/15/2018 4:46:42 PM
42 KLB157113189AfzalpurInstitutionalSportsGeneralConstruction of cricket ground, Cricket pitch and Gallery in Afzalpur town Dist Kalaburagi part IIKRIDL-218/01/2016 141.00 18/01/2016141.00141.0090.00Grallary Roofing Centring Work U/P Play Ground U/P Under Progress3/15/2018 4:47:14 PM
43 KLB157113190AfzalpurInstitutionalSportsGeneralConstruction of compound wall and shelter above Sitting Gallery to Taluka level Stadium at Afzalpur town Dist Kalaburagi KRIDL-225/01/2016 103.75 25/01/2016103.75103.7592.00Compound Wall Completed & Other Nearing Completion Under Progress4/4/2018 10:41:48 AM
44 KLB157113194KalaburagiInstitutionalSportsGeneralProviding and supplying Tar felt sheet water proofing to indoor stadium at C P Stadium in Dist. KalaburagiNK02/03/2017 10.60 02/03/201710.600.002.09Work u/pUnder Progress6/21/2018 2:13:06 PM
45 KLB157113325KalaburagiInstitutionalTechnical EdnGENERALConstn of processed Godown at Agricultural Research Centre, Kalaburagi (excluding eletrification work)KRIDL-226/08/2016 105.86 26/08/2016105.860.0092.00Nearing Completion. Under Progress4/4/2018 10:42:23 AM
46 KLB157113326KalaburagiInstitutionalTechnical EdnGENERALConstn of unprocessed Godown at Agricultural Research Centre, Kalaburagi (excluding eletrification work)KRIDL-226/08/2016 123.89 26/08/2016123.890.00107.00Nearing Completion Under Progress4/4/2018 10:42:38 AM
47 KLB157113327KalaburagiInstitutionalTechnical EdnGENERALConstn of Cold storage at Agricultural Research Centre, Kalaburagi (excluding eletrification work)KRIDL-226/08/2016 110.28 26/08/2016110.280.0055.001St stage Roof Laid. Under Progress4/4/2018 10:42:59 AM
48 KLB157123004KalaburagiInfrastructureRoads & BridgesGeneralFormation of BT road from old jewargi road to PNT cross via Ganadevate to Naganhalli approach road in ward no 54 of KlaburagiPWD KLB21/08/2015 186.80 07/11/2015179.22161.02121.11Minor works balanceUnder Progress4/13/2018 6:34:52 PM
49 KLB157123007KalaburagiInfrastructureRoads & BridgesGeneralImprovement and repair to road from Margutti cross to Bidar Border (via swanth pattwad village) in Kalaburagi Taluka PWD KLB11/03/2016 487.20 13/03/2018487.20403.45330.78Road work completed.KM&HM stones Name Board to be fixed.Under Progress4/13/2018 6:34:20 PM
50 KLB157123096KalaburagiInfrastructureRoads & BridgesGeneralFormation of road from Udanoor village to Minajagi village 6.00 kmPRED13/07/2016 394.65 17/07/2017394.65394.650.002.5Km Sub Grade Completed Under Progress6/1/2018 1:51:44 PM
51 KLB157123130KalaburagiInfrastructureRoads & BridgesGeneralFormation of Road from Aurad (K) village rehabitation centre to Herur village of Kalaburagi talukPRED13/07/2016 275.02 12/01/2017272.80261.6871.57G III Metalling Under ProgressUnder Progress4/17/2018 10:40:41 AM
52 KLB157123162KalaburagiInstitutionalPark GeneralConstruction of Fountain in Makrana marbal 3 no. @ Rajiv Gandhi Theme Park KalaburagiNK22/07/2015 28.02 22/07/201528.020.0029.00Installation of Makarana marble is completed & finishing work completed & electrification work to be doneUnder Progress6/21/2018 2:33:34 PM
53 KLB157123163KalaburagiInstitutionalPark GeneralConstruction of Fountain in Makrana marbal bodhi desing @ Rajiv Gandhi Theme Park KalaburagiNK22/07/2015 10.33 22/07/201510.330.0010.59Installation of Makarana marble is completed & finishing work completed & electrification work to be doneUnder Progress6/21/2018 2:34:04 PM
54 KLB157123164KalaburagiInstitutionalPark GeneralConstruction of Fountain in Makrana marbal 2 no @ Public Exhibition Ground GDA layout KalaburagiNK22/07/2015 18.68 22/07/201518.680.0019.31Installation of makarana marble is completed & finshing work completed & electrification work to be doneUnder Progress6/21/2018 2:36:13 PM
55 KLB157123307KalaburagiInfrastructureWater SupplyGENERALInstallation of WPP plant in Balawad village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.811.91ಪ್ಲಾಂಟ್ ಅಳವಡಿಸಲಾಗಿದೆUnder Progress5/21/2018 12:42:09 PM
56 KLB157123308KalaburagiInfrastructureWater SupplyGENERALInstallation of WPP plant in Thilagul village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಸೆಲ್ಟರ್ ಕಾಮಗಾರಿ ಮುಗಿದಿದೆUnder Progress5/21/2018 1:01:21 PM
57 KLB157123309KalaburagiInfrastructureWater SupplyGENERALInstallation of WPP plant in Venkat Bannur village under JalamrithRWS11/01/2016 4.45 11/01/20164.453.810.00ಪ್ಲಾಂಟ್ ಅಳವಡಿಸಲಾಗಿದೆUnder Progress5/21/2018 1:01:45 PM
58 KLB157623234KalaburagiInstitutionalCollegeGeneralConstn of Govt ITI College renovation work at Kalaburagi NK08/03/2016 19.80 08/03/201619.800.003.00Work under progressUnder Progress6/21/2018 3:08:35 PM
59 KLB157623235KalaburagiInstitutionalCollegeGeneralConstn of third floor to Govt Pre University girls college Building at Kalaburagi NK13/01/2016 73.45 13/01/201673.450.0072.55Finishing stageUnder Progress6/21/2018 3:09:49 PM
         4052.03 4017.841931.802048.06