1 BRD152123005BhalkiInfrastructureUrban InfrastructureGeneralNemmadi Uru Bhalki: Town HallPWD20/05/2016 199.40 20/05/2016199.40192.3681.22ROOF laid plastering work under progressUnder Progress3/22/2018 5:10:09 PM
2 BRD152123007BhalkiInfrastructureUrban InfrastructureGeneralConstn of walkway path to Bhalki Minor Irrigation tank in Bidar DistMI 02/02/2016 198.76 02/02/2016198.76198.71197.34 WORK UNDER PROGRESSUnder Progress4/4/2018 11:09:44 AM
3 BRD152123009BhalkiInfrastructureUrban InfrastructureGeneralProviding Chain link fencing to the Bhalki Minor Irrigation tank in Bidar DistMI 02/02/2016 109.09 02/02/2016109.09107.19105.42work in ProgressUnder Progress4/4/2018 11:10:08 AM
4 BRD152123010BhalkiInfrastructureUrban InfrastructureGeneralConstn of Approach road to Bhalki Minor Irrigation tank from PWD main road in Bidar DistMI 02/02/2016 19.78 02/02/201619.7816.9916.75Work in Progress.Under Progress3/9/2018 6:11:43 PM
5 BRD154113011BidarInstitutionalEducationGeneralProviding water supply to university campus at nirmanahalli in bidar district from bidar water treatment plant at nirmanahalli tandaRWS04/07/2015 36.50  36.5027.6720.05under progressUnder Progress1/29/2018 10:59:33 AM
         563.53 563.53542.92420.78