Sl.No | Workcode | Tal_Name | Sub Type | Sector | Category | WORK NAME | AGENCY NAME | Plan App DATE | Allocation | Adm APP Date | ADM Amt | WO Amt | EXP | Stages of work | Status Type Name | Last Modified |
1
| BLY15R1113030 | Sirguppa | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Bairapur | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 12.08 | Column upto Lintel Level Block masonry work upto Cill Level | Under Progress | 3/16/2018 12:12:07 PM |
2
| BLY15R1123083 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kudadarhal -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 1.97 | Under Progress | Under Progress | 4/4/2018 12:09:40 PM |
3
| BLY15R1123084 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kenchangudda - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.88 | Under Progress | Under Progress | 4/4/2018 12:03:09 PM |
4
| BLY15R1123085 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in nadaga - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.88 | Under Progress | Under Progress | 4/4/2018 12:03:25 PM |
5
| BLY15R1123086 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in K.Suguru - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 1.97 | Under Progress | Under Progress | 4/4/2018 12:10:18 PM |
6
| BLY15R1123087 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Bagawadi- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 1.97 | Under Progress | Under Progress | 4/4/2018 12:10:00 PM |
7
| BLY15R1123089 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Karuru - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 1.97 | Under Progress | Under Progress | 4/4/2018 12:10:34 PM |
8
| BLY15R1123090 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Balkundi - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.89 | Under Progress | Under Progress | 4/4/2018 12:05:11 PM |
9
| BLY15R1123091 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Daruru - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 1.96 | Under Progress | Under Progress | 3/8/2018 11:53:50 AM |
10
| BLY15R1123092 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hacholli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| 29/06/2016 | 2.47 | 2.47 | 0.78 | Under Progress | Under Progress | 4/4/2018 12:02:52 PM |
11
| BLY15R1123094 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in A.Dibbadahalli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 4:48:27 PM |
12
| BLY15R1123261 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kudadarhal -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 5:52:43 PM |
13
| BLY15R1123262 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kenchangudda -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 5:53:21 PM |
14
| BLY15R1123263 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in nadaga - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 5:54:06 PM |
15
| BLY15R1123264 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in K.Suguru -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:14:17 AM |
16
| BLY15R1123265 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Bagawadi-Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:15:14 AM |
17
| BLY15R1123266 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Badguppa - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:15:59 AM |
18
| BLY15R1123267 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Karuru - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:16:34 AM |
19
| BLY15R1123268 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Balkundi - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 1.97 | | Under Progress | 4/4/2018 12:08:40 PM |
20
| BLY15R1123269 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Daruru - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 1.97 | | Under Progress | 4/4/2018 12:08:14 PM |
21
| BLY15R1123270 | Sirguppa | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hacholli - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:18:05 AM |
22
| BLY15R2113022 | Bellary | Institutional | Education | General | Constn of proposed 6 class rooms to Govt Commerce and Management college in Ballari town (ground floor) | NK | 14/03/2016 |
72.81
| 14/03/2016 | 72.81 | 72.81 | 60.00 | Finishing stage | Under Progress | 4/4/2018 3:17:37 PM |
23
| BLY15R2113023 | Bellary | Institutional | Education | General | Constn of 6 class rooms to Govt Commerce and Management college in Ballari town (first floor) | NK | 14/03/2016 |
48.89
| 14/03/2016 | 48.89 | 48.89 | 32.00 | Finishing stage | Under Progress | 4/4/2018 3:17:49 PM |
24
| BLY15R2113029 | Bellary | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Channal | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 22.67 | Roof Laid | Under Progress | 4/4/2018 3:18:38 PM |
25
| BLY15R2123002 | Bellary | Infrastructure | Water Supply | General | ಕುಡುತಿನಿ ಗ್ರಾಮದಲ್ಲಿ ಕುಡಿಯುವ ನೀರು ಸರಬರಾಜು ಹೆಚ್ಚುವರಿಯಾಗಿ ಪಂಪ್ ಹೌಸ್ ಒಳಗೊಂಡಂತೆ 2 ನೇ ಹಂತದ ಪೈಪಲೈನ್ ಕಾಮಗಾರಿ | RWS | 17/11/2015 |
140.00
| 05/02/2016 | 139.98 | 138.53 | 103.57 | Laying of Pipe line completed. Pump house yet to be started | Under Progress | 10/11/2017 5:17:36 PM |
26
| BLY15R2123003 | Bellary | Infrastructure | Water Supply | General | ಕುಡುತಿನಿ ಕೆರೆಗೆ ಹೆಚ್ಚುವರಿ ಪೈಪಲೈನ ಹಾಕುವುದು | RWS | 05/02/2016 |
130.00
| 05/02/2016 | 129.98 | 127.99 | 116.52 | work nearing compelition | Under Progress | 10/11/2017 5:18:16 PM |
27
| BLY15R2123021 | Bellary | Institutional | Education | General | Constn of ground floor library building for Govt Commerce and Management college in Ballari town | NK | 14/03/2016 |
63.55
| 14/03/2016 | 63.55 | 63.55 | 27.68 | Roof to be casted | Under Progress | 4/4/2018 3:20:18 PM |
28
| BLY15R2713001 | Bellary | Institutional | Hostel | General | Coir mattress and pillows on DGSND to BCM hostels | HKRDB | 13/01/2017 |
3.87
| 13/01/2017 | 3.87 | 0.00 | 0.00 | under progress | Under Progress | 11/3/2017 12:12:16 PM |
29
| BLY15R2713002 | Bellary | Institutional | Water Supply | General | SUPPLY, INSTALLATION, TRAINING OF R.O WATER PURIFICATION PLANTS WITH DISPENSING UNITS OF CAPACITY 250 / 500 / 1000 LPH REQUIRED AT DIFFERENT LOCATIONS OF BELLARY DISTRICT UNDER MACRO PROJECTS OF HKRDB KALABURAGI UNDER JALAMRIT 2015-16 REAPPROPRIATION”.IND-132 | HKRDB | 08/08/2016 |
66.81
| 08/08/2016 | 66.81 | 0.00 | 20.00 | under progress | Under Progress | 11/3/2017 12:14:50 PM |
30
| BLY15R2713003 | Bellary | Institutional | Water Supply | General | SUPPLY, INSTALLATION, TRAINING OF R.O WATER PURIFICATION PLANTS WITH DISPENSING UNITS OF CAPACITY 500 / 1000 LPH REQUIRED AT HB HALLI TALUKA OF BELLARY DISTRICT UNDER MACRO PROJECTS OF HKRDB KALABURAGI UNDER JALAMRIT 2015-16 REAPPROPRIATION”.IND-133 | HKRDB | 16/07/2016 |
117.83
| 16/07/2016 | 117.83 | 0.00 | 64.39 | Under progress | Under Progress | 3/16/2018 3:56:52 PM |
31
| BLY15R3121080 | Hospet | Infrastructure | Water Supply | SCP | Water Purification Plant in Hanumanahalli Basapur -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.36 | Under Progress | Under Progress | 4/7/2018 12:07:11 PM |
32
| BLY15R3122081 | Hospet | Infrastructure | Water Supply | TSP | Water Purification Plant in Garaga -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.37 | Under Progress | Under Progress | 4/4/2018 12:11:15 PM |
33
| BLY15R3123078 | Hospet | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kampli town 2 Concrete Platform Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.37 | UNDER PROGRESS | Under Progress | 4/4/2018 12:02:26 PM |
34
| BLY15R3123271 | Hospet | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kampli town 1- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 4:55:37 PM |
35
| BLY15R3123272 | Hospet | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kampli town 2 -- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 4:57:27 PM |
36
| BLY15R3123273 | Hospet | Infrastructure | Water Supply | SCP | Water Purification Plant in Venktapur -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 5:01:03 PM |
37
| BLY15R3123274 | Hospet | Infrastructure | Water Supply | SCP | Water Purification Plant in Hanumanahalli Basapur -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 5:00:42 PM |
38
| BLY15R3123275 | Hospet | Infrastructure | Water Supply | TSP | Water Purification Plant in Garaga -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/3/2018 4:59:40 PM |
39
| BLY15R4113014 | Sandoor | Institutional | Sports | General | Constn of compound wall Taluka Stadium at Sandur, Bellary dist | NK | 09/03/2016 |
61.22
| 09/03/2016 | 61.22 | 61.22 | 3.10 | Foundation work under progress | Under Progress | 4/4/2018 3:25:23 PM |
40
| BLY15R4113034 | Sandoor | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Yarrainhana Halli | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 7.95 | Lintel completed | Under Progress | 4/4/2018 3:25:57 PM |
41
| BLY15R4113035 | Sandoor | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Talur | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 12.58 | Lintel Level | Under Progress | 4/4/2018 3:26:12 PM |
42
| BLY15R4123009 | Sandoor | Institutional | Transport | General | ಬಂಡ್ರಿ ಗ್ರಾಮದಲ್ಲಿ ಸಾರ್ವಜನಿಕ ಬಸ್ ನಿಲ್ದಾಣ ನಿರ್ಮಾಣ. | PRED-B | 17/08/2015 |
50.00
| 04/01/2016 | 48.85 | 44.99 | 11.42 | Finishing work under progress | Under Progress | 10/21/2017 12:00:29 PM |
43
| BLY15R4123010 | Sandoor | Institutional | Transport | General | ಯಶವಂತನಗರ ಗ್ರಾಮದಲ್ಲಿ ಸಾರ್ವಜನಿಕ ಬಸ್ ನಿಲ್ದಾಣ ನಿರ್ಮಾಣ. | PRED-B | 17/08/2015 |
58.58
| 04/01/2016 | 56.88 | 56.54 | 26.59 | Finishing work under progress | Under Progress | 11/20/2017 11:47:17 AM |
44
| BLY15R4123011 | Sandoor | Institutional | Transport | General | ತಾರಾನಗರ ಗ್ರಾಮದಲ್ಲಿ ಸಾರ್ವಜನಿಕ ಬಸ್ ನಿಲ್ದಾಣ ನಿರ್ಮಾಣ. | PRED-B | 17/08/2015 |
50.00
| 04/01/2016 | 48.85 | 44.85 | 0.51 | Roof level | Under Progress | 2/2/2018 10:01:40 PM |
45
| BLY15R5113031 | Kudligi | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Kakkuppi | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 23.55 | Ground floor Finishing stage | Under Progress | 4/23/2018 1:10:27 PM |
46
| BLY15R5121112 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Kyasankere- Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:52:25 PM |
47
| BLY15R5121114 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at valase- Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:52:36 PM |
48
| BLY15R5121115 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at valase - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 4:55:58 PM |
49
| BLY15R5121116 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Maruru- Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:16:57 PM |
50
| BLY15R5121117 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Maruru- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 4:56:39 PM |
51
| BLY15R5121118 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Motikal Tanda - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:50:09 PM |
52
| BLY15R5121119 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Motikal Tanda - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 4:57:22 PM |
53
| BLY15R5121120 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Boranhalli- Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:50:22 PM |
54
| BLY15R5121121 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Boranhalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 4:58:10 PM |
55
| BLY15R5121122 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Bhattanhalli- Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:50:39 PM |
56
| BLY15R5121123 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Bhattanhalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 4:59:01 PM |
57
| BLY15R5121124 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Kottur Town Hyalya road SC colony (19th ward)- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:35:01 AM |
58
| BLY15R5121125 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Kottur Town Hyalya road SC colony (19th ward)- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:25:22 PM |
59
| BLY15R5121126 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at chikkajogihalli Tanda- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:35:29 AM |
60
| BLY15R5121127 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at chikkajogihalli Tanda- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.47 | Under Progress | Under Progress | 4/7/2018 12:07:49 PM |
61
| BLY15R5121128 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Khanahosalli SC colony- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:36:03 AM |
62
| BLY15R5121130 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Srikanthapur Tanda- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:36:54 AM |
63
| BLY15R5121131 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Srikanthapur Tanda- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.47 | Under Progress | Under Progress | 4/7/2018 12:07:31 PM |
64
| BLY15R5121132 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Ammenhalli tanda- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:37:22 AM |
65
| BLY15R5121133 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at Ammenhalli tanda- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/8/2018 1:09:51 PM |
66
| BLY15R5121134 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at chinnenhalli Tanda- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:37:54 AM |
67
| BLY15R5121136 | Kudligi | Infrastructure | Water Supply | SCP | Water Purification plant at B.D.Gudda - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:38:26 AM |
68
| BLY15R5122138 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Advisurwanahalli- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:32:58 AM |
69
| BLY15R5122139 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Advisurwanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:02:12 PM |
70
| BLY15R5122140 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at geddalgatte - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:33:26 AM |
71
| BLY15R5122141 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at geddalgatte - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:02:52 PM |
72
| BLY15R5122142 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Arjunachinnenahalli- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:33:52 AM |
73
| BLY15R5122143 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Arjunachinnenahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:10:37 PM |
74
| BLY15R5122144 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Kadekol- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:19:47 AM |
75
| BLY15R5122145 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Kadekol- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.47 | Under Progress | Under Progress | 4/4/2018 12:11:28 PM |
76
| BLY15R5122146 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at A.Karnarhatti- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:20:31 AM |
77
| BLY15R5122147 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at A.Karnarhatti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:28:18 PM |
78
| BLY15R5122148 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Jarmali- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:21:22 AM |
79
| BLY15R5122149 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Jarmali- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:05:08 PM |
80
| BLY15R5122150 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Soladahalli- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:22:19 AM |
81
| BLY15R5122152 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Ramdurga- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:34:27 AM |
82
| BLY15R5122153 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Ramdurga- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 5:06:10 PM |
83
| BLY15R5122154 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Kartikenhatti- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:22:57 AM |
84
| BLY15R5122156 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Hude- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:23:36 AM |
85
| BLY15R5122158 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Magapur- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:26:15 AM |
86
| BLY15R5122159 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Magapur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 5:07:40 PM |
87
| BLY15R5122160 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Narsihagiri- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:26:40 AM |
88
| BLY15R5122161 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Narsihagiri- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.55 | Under Progress | Under Progress | 3/7/2018 5:08:26 PM |
89
| BLY15R5122162 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Ramsagarhatti- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:27:17 AM |
90
| BLY15R5122163 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at Ramsagarhatti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:09:08 PM |
91
| BLY15R5122164 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at chadrashekharpur- Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:27:47 AM |
92
| BLY15R5122165 | Kudligi | Infrastructure | Water Supply | TSP | Water Purification plant at chadrashekharpur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 2.47 | Under Progress | Under Progress | 4/4/2018 12:11:41 PM |
93
| BLY15R5123093 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in T.Kallahalli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:10:21 PM |
94
| BLY15R5123095 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Ranganathanhalli -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:11:12 PM |
95
| BLY15R5123096 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hurlihal - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/7/2018 5:11:57 PM |
96
| BLY15R5123097 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Harakbavi - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.53 | Under Progress | Under Progress | 3/7/2018 5:12:37 PM |
97
| BLY15R5123100 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Amalapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.53 | Under Progress | Under Progress | 3/7/2018 5:13:44 PM |
98
| BLY15R5123104 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Ayyanhalli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:57:05 PM |
99
| BLY15R5123105 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in APMC in Kottur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.60
| | 2.60 | 2.60 | 0.55 | Under Progress | Under Progress | 3/8/2018 1:29:33 PM |
100
| BLY15R5123106 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Rajiv Gandhi Nagar in Kottur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.60
| | 2.60 | 2.60 | 0.55 | Under Progress | Under Progress | 3/8/2018 1:30:23 PM |
101
| BLY15R5123107 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kalapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:31:19 PM |
102
| BLY15R5123108 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Siddapur waddarhatti cross - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.53 | Under Progress | Under Progress | 3/8/2018 1:14:22 PM |
103
| BLY15R5123109 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in chikka Jogihalli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:13:20 PM |
104
| BLY15R5123110 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Immadapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.54 | Under Progress | Under Progress | 3/8/2018 1:33:25 PM |
105
| BLY15R5123240 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in A.Dibbadahalli -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:43:16 AM |
106
| BLY15R5123241 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Ranganathanhalli -Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:43:53 AM |
107
| BLY15R5123242 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hurlihal - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:44:23 AM |
108
| BLY15R5123243 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Harakbavi - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:48:59 AM |
109
| BLY15R5123244 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Ammankere - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work u/p | Under Progress | 3/9/2018 4:23:16 PM |
110
| BLY15R5123245 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Balapur - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 4:24:54 PM |
111
| BLY15R5123246 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Amalapur - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:49:31 AM |
112
| BLY15R5123247 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hyalya - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 11:58:20 AM |
113
| BLY15R5123248 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Hosa Kodihalli - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 11:59:27 AM |
114
| BLY15R5123249 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Bewur - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:39:04 AM |
115
| BLY15R5123250 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Ayyanhalli - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:39:34 AM |
116
| BLY15R5123251 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Taluka Hospital in Kottur - Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
1.57
| | 0.00 | 0.00 | 0.00 | | Under Progress | 1/25/2018 3:34:38 PM |
117
| BLY15R5123252 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in APMC in Kottur - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:55:57 PM |
118
| BLY15R5123253 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Rajiv Gandhi Nagar in Kottur - Pre-fab hut (4.88m x 9.76m) | KRIDL-H | 17/01/2018 |
2.53
| 17/01/2018 | 2.53 | 2.53 | 1.01 | cabin work U/p | Under Progress | 3/9/2018 5:56:08 PM |
119
| BLY15R5123254 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Kalapur - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:40:08 AM |
120
| BLY15R5123255 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Siddapur waddarhatti cross - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:40:43 AM |
121
| BLY15R5123256 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in chikka Jogihalli - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:41:16 AM |
122
| BLY15R5123257 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Immadapur - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:41:44 AM |
123
| BLY15R5123258 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in Tulahalli - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.53
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:42:11 AM |
124
| BLY15R51239 | Kudligi | Infrastructure | Water Supply | GENERAL | Water Purification Plant in T.Kallahalli - Pre-fab hut (4.88m x 9.76m) | RWS | 03/03/2018 |
2.60
| | 0.00 | 0.00 | 0.00 | | Under Progress | 3/5/2018 11:42:48 AM |
125
| BLY15R6113032 | Hadagali | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at Bheerabbi | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 27.32 | Ground floor Finishing stage | Under Progress | 4/4/2018 3:29:32 PM |
126
| BLY15R6113033 | Hadagali | Institutional | Social | General | Const of M.Y.Ghorpade GP Building at K.Ayyanahalli | NK | 06/04/2016 |
50.00
| 20/06/2016 | 50.00 | 50.00 | 29.05 | Ground floor Finishing stage, First floor cill Level | Under Progress | 4/4/2018 3:30:09 PM |
127
| BLY15R6123005 | Hadagali | Infrastructure | Roads & Bridges | General | Impts of road from Shastri circle to Sogi circle in Hadagali | PWD-H | 04/10/2016 |
184.60
| 07/11/2016 | 184.60 | 197.74 | 0.00 | Work Started | Under Progress | 11/7/2017 4:48:37 PM |
128
| BLY15R7121217 | H.B.Halli | Infrastructure | Water Supply | SCP | Water Purification plant at Bovi colony- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.48 | UNDER PROGRESS | Under Progress | 3/7/2018 12:04:07 PM |
129
| BLY15R7121223 | H.B.Halli | Infrastructure | Water Supply | SCP | Water Purification plant at Warala - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.59 | Under Progress | Under Progress | 3/7/2018 12:51:36 PM |
130
| BLY15R7121225 | H.B.Halli | Infrastructure | Water Supply | SCP | Water Purification plant at Kalla Halli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.53 | Under Progress | Under Progress | 3/7/2018 12:54:56 PM |
131
| BLY15R7121227 | H.B.Halli | Infrastructure | Water Supply | SCP | Water Purification plant at Marbihal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.58 | Under Progress | Under Progress | 3/7/2018 12:56:14 PM |
132
| BLY15R7122169 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Hosa Chinmalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:12:42 PM |
133
| BLY15R7122171 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Nanipur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:22:59 PM |
134
| BLY15R7122173 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Kanvi Nayakanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.57 | Under Progress | Under Progress | 3/7/2018 1:27:56 PM |
135
| BLY15R7122175 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Adakanbavi- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.90 | Under Progress | Under Progress | 4/16/2018 10:53:42 AM |
136
| BLY15R7122177 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Lokappanhola- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:29:48 PM |
137
| BLY15R7122179 | H.B.Halli | Infrastructure | Water Supply | TSP | Water Purification plant at Byalal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.87 | Under Progress | Under Progress | 4/16/2018 10:51:25 AM |
138
| BLY15R7123181 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant near Ramnagar Sinima manjanna house- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:32:58 PM |
139
| BLY15R7123183 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Vardapur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:33:52 PM |
140
| BLY15R7123185 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Anka Samudra- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:34:52 PM |
141
| BLY15R7123187 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at B.G. Halli 2- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:36:20 PM |
142
| BLY15R7123189 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Shigenahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:38:35 PM |
143
| BLY15R7123191 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Tambrahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:38:00 PM |
144
| BLY15R7123195 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Arlihalli Kuradagadi Housing Board Park- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:41:11 PM |
145
| BLY15R7123197 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Ram Rahim Nagar- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:44:20 PM |
146
| BLY15R7123199 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Uppinayakanhalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.59 | Under Progress | Under Progress | 3/7/2018 1:45:06 PM |
147
| BLY15R7123201 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Vallabhapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:47:41 PM |
148
| BLY15R7123203 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Jalinagar- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 2.88 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:48:21 PM |
149
| BLY15R7123205 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Ramnagar Raitar Oni- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.33 | Under Progress | Under Progress | 3/7/2018 1:53:36 PM |
150
| BLY15R7123207 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Hagari Bommanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.48 | Under Progress | Under Progress | 3/7/2018 1:56:58 PM |
151
| BLY15R7123209 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Uppargatti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 16/02/2018 |
2.88
| | 2.88 | 1.30 | 0.48 | Under Progress | Under Progress | 3/8/2018 11:39:47 AM |
152
| BLY15R7123211 | H.B.Halli | Infrastructure | Water Supply | GENERAL | Water Purification plant at Advi Anand Devanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water. | RWS | 26/05/2016 |
2.47
| | 2.47 | 2.47 | 0.59 | Under Progress | Under Progress | 3/7/2018 2:05:21 PM |
| | | | | | | | | 1734.78 | | 1603.38 | 1414.79 | 676.80 | | | |