LIST OF Under Progress MICRO WORKS

Taluka

Sub Type

Sub Sector

Category

Agency


Sl.NoWorkcodeTalukaSub TypeSectorCategoryWork NameAgencyPlan Approval DateAllocationWork Order AmountExpenditureWork Stage
1 KLB145123133JewargiInfrastructureRoads & BridgesGeneralConstn of 2 bridges between Yadrami and Yatnal canal (Bridge –II 50 mtrs span) in Jewargi talukaPWD KLB20/12/2017 168.35 161.1243.35Bridge completion. approach under progress.
2 KLB145123134JewargiInfrastructureRoads & BridgesGeneralConstn of 2 bridges between Yadrami and Yatnal canal (Bridge –I 50 mtrs span) in Jewargi talukaPWD KLB20/12/2017 145.00 131.4337.45Four unit top slab completed. Further work in progress.
3 KLB146113154SedamInstitutional Culture ArtsGeneralCompletion of Suvarna Karnataka Bhavan @ Sedam Town (Compound wall, internal road, box culvert, street light)KRIDL-205/02/2017 51.90 0.0038.00Compound Wall Work U/P
4 KLB147113075KalaburagiInfrastructureTheme ParkGeneralConstruction of Insectorium at Rajiv Gandhi theme park, KalaburagiNK25/04/2015 47.03 47.0354.09Roof concrete work completed.
5 KLB147113076KalaburagiInfrastructureTheme ParkGeneralConstruction of Aquarium block at Rajiv Gandhi theme park, KalaburagiNK25/04/2015 39.38 39.3819.56Roof slab centering work to be start.
6 KLB147113077KalaburagiInfrastructureTheme ParkGeneralConstruction of Kids house at Rajiv Gandhi theme park, KalaburagiNK09/12/2015 49.86 49.8652.56Roof slab casted.
7 KLB147113078KalaburagiInfrastructureTheme ParkGeneralConstruction of Fun complex & 7D theater at Rajiv Gandhi theme park, KalaburagiNK12/06/2015 162.10 162.10120.23Work stopped (Awaiting for further order by HKRDB Secretary)
8 KLB147113099KalaburagiInstitutionalExhibition & Concert GroundGeneralConstruction of Concert Stage at Public exhibition ground, Kotnoor D park KalaburagiNK06/06/2015 63.13 67.4576.01Work stopped (Awaiting for further order by HKRDB Secretary)
9 KLB147123050KalaburagiInfrastructureRoads & BridgesGeneralGulbarga Airport Road Connectivity Package – Shifting of poles – Jayanagar Main Road (From Sedam Main Road to Kusnoor Road)PWD KLB08/04/2015 3.11 2.350.00Work under progress.
10 KLB147123068KalaburagiInfrastructureRoads & BridgesGeneralConstruction of footpath at Bhavikatti road from circle to chowk police station kalaburagi.PWD KLB06/04/2015 11.45 9.240.00Work under progress.
      TOTAL  741.31669.96441.25