LIST OF Not Started MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Feedback
1 BDR1611253029AuradInfrastructureUrban InfrastructureGeneralNemmadi Uru Aurad : Town HallPWD 09/12/2016 192.36  0.000.000.00 Suitable Site not yet handed overby CMC. previously 2 sites were shown by cmc one is under litigation and one is not fit for type desigen of building as per hkrdb direction section officer has approached to consultant for change of type design but consultant said that not possible to change the type design proposed to drop
2 BDR162123068HumnabadInfrastructureUrban InfrastructureGENERALHumnabad Reading CenterPWD29/08/2017 95.00  0.000.000.00DPR prepared by consultant but site not yet handed over by CMC
      TOTAL  287.36 0.000.000.00