LIST OF Under Progress MACRO WORKS

  Workcode Taluka Type Subtype Category Work Name Agency Plan Approved Date Allocation ADM Approved Date ADM Amount Work Order Amt Exp Stages of Work Status Not Started Under Progress Completed Feedback
1 BLY161113027SirguppaInstitutionalEducationGeneralConstruction of Urdu School and Toilet Block at Sirguppa TownNK09/02/2017 70.00 09/02/201770.0070.0040.31GF and FF Finishing stageUnder Progress
2 BLY161113028SirguppaInstitutionalEducationGeneralConstruction of Two Class Rooms To Govt PU College Tekkalakote, Siruguppa Taluk, Bellary District.NK03/09/2016 16.35 03/09/201616.3516.3512.15Roof Laid plastering work under progressUnder Progress
3 BLY161113029SirguppaInstitutionalEducationGeneralConstruction of First Floor Laboratory To Govt PU College Tekkalkote, Siruguppa Taluka, Bellary District.NK03/09/2016 13.29 03/09/201613.2913.290.89Column upto Roof LevelUnder Progress
4 BLY161113030SirguppaInstitutionalEducationGeneralConstrution of Ground floor Laboratory To Govt PU College Tekkalakote, Sirugappa Taluka, Bellary District.NK03/09/2016 16.98 03/09/201616.9816.985.40Roof Laid Plastering work under progressUnder Progress
5 BLY161113031SirguppaInstitutionalEducationGeneralConstruction of One Class Room To Govt Pu College Tekkalakote, Siruguppa Taluka, Bellary District.NK03/09/2016 9.12 03/09/20169.129.126.02Roof Laid Block masonry under progressUnder Progress
6 BLY161113032SirguppaInstitutionalEducationGeneralConstruction of One class Class Room To Govt PU college Tekkalakote, Siruguppa Taluka, Bellary District.NK03/09/2016 9.12 03/09/20169.129.120.65column Upto Roof Level Under Progress
7 BLY161113033SirguppaInstitutionalEducationGeneralConstruction of Toilet Block To Govt PU College @Tekkalakote, Siruguppa Taluk, Bellary DistrictNK03/09/2016 16.04 03/09/201616.0416.046.29finishing stageUnder Progress
8 BLY161423103SirguppaInfrastructureRoads & BridgesGeneralಬಳ್ಳಾರಿ ಜಿಲ್ಲೆ ಸಿರುಗುಪ್ಪ ತಾಲ್ಲೂಕಿನ ಕೆ ಬೆಳಗಲ್ ಗ್ರಾಮ ಪಂಚಾಯ್ತಿ ವ್ಯಾಪ್ತಿಯ ಕೆ ಬಳಗಲದಿಂದ ಗೆಜ್ಜಾಳವರೆಗಿನ ರಸ್ತೆ ಕಾಮಗಾರಿPRED-B 14/12/2016 31.50  0.000.000.00under progressUnder Progress
9 BLY162113001BellaryInstitutionalSocialGeneralM.Y Ghorpade G. P Building at B D halli in Bellary talukaNK27/10/2016 50.00 03/02/201750.0050.0012.98Lintel LevelUnder Progress
10 BLY162113025BellaryInstitutionalEducationGeneralConstruction of Government PU College at Kurugodu Bellary (D)NK30/12/2016 196.22 30/12/2016196.22196.2248.98Roof sheltering work under progressUnder Progress
11 BLY162113036BellaryInstitutionalSocialGeneralProviding obstacles at Karnataka State Emergency Response Training Academy (Regional Home guards Training Centre) at Meenhalli village, Bellary talukaNK10/04/2016 30.50 04/10/201630.5030.5010.18Finishing stageUnder Progress
12 BLY162113044BellaryInstitutionalEducationGeneralConstruction of Additional Class Room to Higher Primary School at Moka Bellary TalukaNK 25/02/2017 26.00 01/03/201726.0026.006.76Roof Sheltering work under progressUnder Progress
13 BLY162113081BellaryInfrastructureWater SupplyGeneralConstn of OHT and extension of pipeline at Chanalu village in Bellary TalukaRWS07/11/2016 32.46 22/12/201632.4631.9914.19Laying of DI pipe completed. Construction of OHT under progressUnder Progress
14 BLY162113089BellaryInstitutionalHostelGeneralConst of OBC Students Girls Hostel at Vijaynagar Sri. Krinadevarayya University Jnanasagara Campus Ballary.NK17/02/2017 180.14 09/03/2017179.45179.4529.28Lintel LevelUnder Progress
15 BLY162123005BellaryInfrastructureRoads & BridgesGeneralFormation of Drain at Diwakara Babu Layout in Ward No. 20 Bellary TalukaCMC Bellary 07/11/2016 70.00 05/02/201770.0069.2320.34Drain work is in progress.Under Progress
16 BLY162123006BellaryInfrastructureRoads & BridgesGeneralImprovements to Roads at Mahateja Nagar in BellaryCMC Bellary 22/12/2016 66.80 22/12/201666.8065.1234.69Culvert construction is in progress.Under Progress
17 BLY162123008BellaryInfrastructureRoads & BridgesGeneralImprovements to roads from Mundargi Main Road to Ananthapur By Pass in BellaryCMC Bellary 22/12/2016 89.95 22/12/201689.9589.940.00GSB to be laidUnder Progress
18 BLY162123018BellaryInfrastructureRoads & BridgesGeneralConstruction of CC Road from Tinker Beedi culvert to Koul Bajar main road Mohammadi school beside big Drain in Bellary CityCMC Bellary 22/12/2016 47.50 22/12/201647.2346.8135.50cc road is in progressUnder Progress
19 BLY162123020BellaryInfrastructureRoads & BridgesGeneralConstruction of Storm water Drain beside Divakar Babu Layout (VV Sangha Land to Railway Track) Road in Bellary CityCMC Bellary 22/12/2016 30.00 22/12/201619.7519.090.00Excavation for drain is in progressUnder Progress
20 BLY162123021BellaryInfrastructureRoads & BridgesGeneralFormation of Drain at Nala Street in Ward No. 24 in Bellary CityCMC Bellary 06/01/2017 110.00 30/03/2017105.50104.250.00First stretch of drain is completed and second stretch is to be started. Under Progress
21 BLY162123026BellaryInstitutionalEducationGeneralProviding RCC Roof to Existing class rooms and renovation at Govt. P.U. College, BellaryNK05/02/2017 164.10 05/02/2017164.10164.1029.68out of 13 class room ,6 class room concrete work finishing stage 7 rooms concrete work under progressUnder Progress
22 BLY162123042BellaryInfrastructureUrban InfrastructureGeneralConstruction of Development work for Greve-Yard at Cowl Bazar, BellaryNK 21/04/2017 22.58 21/04/201722.5822.583.3660% work completed further work site problem Under Progress
23 BLY162123051BellaryInfrastructureRoads & BridgesGeneralImprovement to road from Ch: 10380 km of Kuriganur Distributory to Chanal village by metalling Ashaphalting from km 0.00 to 4.20 including structures under Kuriganur Distributory of RBLLC.PMGSY-B28/02/2017 260.00 30/03/2017260.00251.320.00Subgrade completed .CD works under progress.Under Progress
24 BLY162123059BellaryInfrastructureRoads & BridgesGeneralConstruction of Two CC roads in Mariammanahalli village in Bellary Dist.PRED-B 09/01/2017 47.72 17/07/201747.7246.690.00under progressUnder Progress
25 BLY162123060BellaryInstitutionalEducationGeneralConstruction of 3 Nos. Class rooms at Dasaranagenahalli in Bellary TalukaPRED-B 10/01/2017 21.00 08/03/201721.0019.8312.22Finishing work under progressUnder Progress
26 BLY162123125BellaryInfrastructureOthersGENERALಬಳ್ಳಾರಿ ನಗರದ ಟಿ.ಎಸ್ ನಂ: 962/3 ಟೀಚರಸ್ ಕಾಲೋನಿ ನೆಲ್ಲ ಚೆರವು ಪ್ರದೇಶದಲ್ಲಿ ಪಾರ್ಕ ಅಭಿವೃದ್ಧಿ ಪಡಿಸುವುದು.NK07/03/2017 31.00 16/12/201722.5022.500.00compound wall 75% completed Footpath work under progressUnder Progress
27 BLY162223105BellaryInfrastructureRoads & BridgesGENERALಚಾನಾಳು ಗ್ರಾಮದಲ್ಲಿ low level causeway ನಿರ್ಮಾಣ ಮಾಡುವ ಕುರಿತುPMGSY-B27/05/2017 42.50 17/11/201742.5038.570.00 Foundation , laying of pipes Completed. Construction of Returns under progress Under Progress
28 BLY162223106SandoorInfrastructureRoads & BridgesGENERALಕುಡುತಿನಿ ಗ್ರಾಮದ ವಿವಿಧ ವಾರ್ಡಗಳಲ್ಲಿ ಸಿ.ಸಿ. ರಸ್ತೆ ಮತ್ತು ಚರಂಡಿ ನಿರ್ಮಾಣPRED-B26/05/2017 40.00 27/12/201740.0034.910.00Earthwork under progressUnder Progress
29 BLY163113063HospetInstitutionalEducationGeneralConstruction of 4 School Rooms of Govt. High School in Ward No. 15-31 in Nehru Colony, HospetPRED-B 08/12/2016 32.60 08/12/201630.340.000.00under progressUnder Progress
30 BLY163113064HospetInstitutionalEducationGeneralConstruction of 4 Class rooms Govt. PU College (High School Divn.) TB Dam in Hospet TalukaPRED-B 22/11/2016 32.94 20/03/201734.2829.900.00Finishing work under progressUnder Progress
31 BLY163113082HospetInfrastructureWater SupplyGeneralProviding water supply scheme with OHT and DI pipe line for W.No. 07 in Kampli TownRWS09/12/2016 91.00 09/12/20160.000.000.00Estimate submitted for ADM approvalUnder Progress
32 BLY163123077HospetInfrastructureRoads & BridgesGeneralImprovement of and Asphalting Road Kottal to Janur road from 0.00 km to 2.00 km in Hospet TalukaPWD-B 04/11/2016 114.08 10/02/2017156.86155.0656.86WMM 1st layer Work completed & WMM 2nd layer work under progress Under Progress
33 BLY164123078SandoorInfrastructureRoads & BridgesGeneralConstruction of road drains in Ward No. 1, 10, 22, 13, 18 & 22 of Sandur Municipal AreaPWD-B 12/04/2017 196.00 24/10/2017186.00183.3840.69RCC Drain work & WMM work in road under progress Under Progress
34 BLY164123079SandoorInfrastructureRoads & BridgesGeneralಸಂಡೂರು ತಾಲೂಕಿನ ಕುರೇಕುಪ್ಪ ಪುರಸಭೆ ವ್ಯಾಪ್ತಿಯಲ್ಲಿ ಬರುವ ವಾರ್ಡ ನಂ: 2,7,8,11,15,16,20,21 ಮತ್ತು 22 ರಲ್ಲಿ ರಸ್ತೆ ಮತ್ತು ಚರಂಡಿ ನಿರ್ಮಾಣ.PWD-B 08/12/2016 100.00 12/12/2017100.0089.990.00Out of 7 wards, 2 wards CC Road work completed & in remaining wards under progress Under Progress
35 BLY164123080SandoorInfrastructureRoads & BridgesGeneralConstruction of road and drains in Kudithini Pattana Panchayat limits of Sandur VillagePWD-B 12/04/2017 199.50 16/09/2017188.50186.23136.29Work nearing completion Under Progress
36 BLY164123104SandoorInfrastructureNemmadi UruGENERALConstruction of Town Hall fro Nemmadi Uru at Sandoor Town in BellaryPWD-B04/26/2017 187.50 26/02/2018187.96184.290.00Dismantling work to be doneUnder Progress
37 BLY166123049HadagaliInfrastructureNemmadi UruGeneralNemmadi Uru Hadgali : Town HallNK 13/11/2016 186.86 28/01/2017184.29184.2936.52Plinth CompletedUnder Progress
38 BLY166123069HadagaliInfrastructureRoads & BridgesGeneralImprovements to road from Govindapura Tanda to Advimallinakeri Tanda in Huvinahadagali TalukaPRED-H18/01/2017 49.27 18/01/201749.2748.6438.75Phy.completed Under Progress
39 BLY167123114H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at H.Obalapur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS13/01/2017 2.47 13/01/20172.472.470.00CompletedUnder Progress
40 BLY167123116H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Chikkasobati- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS13/01/2017 2.47 13/01/20172.472.470.00CompletedUnder Progress
41 BLY167123120H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Kattehola- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS13/01/2017 2.47 13/01/20172.472.470.00CompletedUnder Progress
      TOTAL  2938.03 2810.072729.19638.98