LIST OF Under Progress MICRO WORKS

Taluka

Sub Type

Sub Sector

Category

Agency


Sl.NoWorkcodeTalukaSub TypeSectorCategoryWork NameAgencyPlan Approval DateAllocationWork Order AmountExpenditureWork Stage
1 BLY15R1113030SirguppaInstitutionalSocialGeneralConst of M.Y.Ghorpade GP Building at BairapurNK06/04/2016 50.00 50.0024.07GF Roof Laid FF Roof Level
2 BLY15R1123085SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in nadaga - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.88Physically completed
3 BLY15R1123087SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Bagawadi- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.89Physically completed
4 BLY15R1123089SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Karuru - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.89Physically completed
5 BLY15R1123090SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Balkundi - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.89Physically Completed
6 BLY15R1123092SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Hacholli - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.77Physically Completed
7 BLY15R1123094SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in A.Dibbadahalli - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54Physically completed
8 BLY15R1123261SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Kudadarhal -Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.000.00Physically completed
9 BLY15R1123263SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in nadaga - Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.000.00Physically completed
10 BLY15R1123265SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Bagawadi-Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.000.00Physically completed
11 BLY15R1123266SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Badguppa - Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.000.00Physically completed
12 BLY15R1123267SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Karuru - Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.000.00Physically completed
13 BLY15R1123269SirguppaInfrastructureWater SupplyGENERALWater Purification Plant in Daruru - Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.001.97completed
14 BLY15R2123021BellaryInstitutionalEducationGeneralConstn of ground floor library building for Govt Commerce and Management college in Ballari townNK14/03/2016 63.55 63.5530.23Finishing stage
15 BLY15R3121079HospetInfrastructureWater SupplySCP Water Purification Plant in Venktapur -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.62Physically Completed
16 BLY15R3121080HospetInfrastructureWater SupplySCP Water Purification Plant in Hanumanahalli Basapur -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.57Physically Completed
17 BLY15R3122081HospetInfrastructureWater SupplyTSP Water Purification Plant in Garaga -Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.57Physically completed
18 BLY15R3123077HospetInfrastructureWater SupplyGENERALWater Purification Plant in Kampli town 1- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/10/2017 2.47 2.470.89Physically Completed
19 BLY15R3123078HospetInfrastructureWater SupplyGENERALWater Purification Plant in Kampli town 2 Concrete Platform Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.89Physically Completed
20 BLY15R3123275HospetInfrastructureWater SupplyTSPWater Purification Plant in Garaga -Pre-fab hut (4.88m x 9.76m)RWS03/03/2018 2.60 0.002.36completed
21 BLY15R4113014SandoorInstitutionalSportsGeneralConstn of compound wall Taluka Stadium at Sandur, Bellary distNK 01/12/2018 15.00 61.223.10Foundation work under progress
22 BLY15R4113034SandoorInstitutionalSocialGeneralConst of M.Y.Ghorpade GP Building at Yarrainhana HalliNK06/04/2016 50.00 50.0012.21Roof Level
23 BLY15R4113035SandoorInstitutionalSocialGeneralConst of M.Y.Ghorpade GP Building at TalurNK06/04/2016 50.00 50.0021.38Roof Laid
24 BLY15R4123009SandoorInstitutionalTransportGeneralಬಂಡ್ರಿ ಗ್ರಾಮದಲ್ಲಿ ಸಾರ್ವಜನಿಕ ಬಸ್ ನಿಲ್ದಾಣ ನಿರ್ಮಾಣ.PRED-B17/08/2015 50.00 44.9922.51Finishing work under progress
25 BLY15R4123011SandoorInstitutionalTransportGeneralತಾರಾನಗರ ಗ್ರಾಮದಲ್ಲಿ ಸಾರ್ವಜನಿಕ ಬಸ್ ನಿಲ್ದಾಣ ನಿರ್ಮಾಣ.PRED-B17/08/2015 50.00 44.850.51Roof level
26 BLY15R4123082SandoorInfrastructureWater SupplyGENERAL1000 LPS Water Purification plant with 2000 Liter Tank in siddapur village - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.00Physically Completed
27 BLY15R5121112KudligiInfrastructureWater SupplySCP Water Purification Plant in Choudapur - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed plant need to be erected.
28 BLY15R5121114KudligiInfrastructureWater SupplySCP Water Purification Plant in Valse- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed plant need to be erected.
29 BLY15R5121115KudligiInfrastructureWater SupplySCP Water Purification plant at valase - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55Basement completed,Flooring, Water supply and Electrification is pending.
30 BLY15R5121116KudligiInfrastructureWater SupplySCP Water Purification Plant in Marur -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed plant need to be erected.
31 BLY15R5121117KudligiInfrastructureWater SupplySCP Water Purification plant at Maruru- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
32 BLY15R5121118KudligiInfrastructureWater SupplySCP Water Purification plant at Motikal Tanda - Pre-fab hut (4.88m x 9.76m)KRIDL-H17/01/2018 2.53 2.531.01cabin work U/p
33 BLY15R5121119KudligiInfrastructureWater SupplySCP Water Purification plant at Motikal Tanda - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.55Basement completed,Flooring, Water supply and Electrification is pending.
34 BLY15R5121120KudligiInfrastructureWater SupplySCP Water Purification Plant in Boranahalli R - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed plant need to be erected.
35 BLY15R5121121KudligiInfrastructureWater SupplySCP Water Purification plant at Boranhalli- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55 
36 BLY15R5121122KudligiInfrastructureWater SupplySCP Water Purification Plant in Bhattanahalli Waddarhatti cross - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed plant need to be erected.
37 BLY15R5121123KudligiInfrastructureWater SupplySCP Water Purification plant at Bhattanhalli- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55 
38 BLY15R5121124KudligiInfrastructureWater SupplySCP Water Purification plant at Kottur Town Hyalya road SC colony (19th ward)-1000 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 9.47 0.000.00Basement completed plant need to be erected.
39 BLY15R5121125KudligiInfrastructureWater SupplySCP Water Purification plant at Kottur Town Hyalya road SC colony (19th ward)- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
40 BLY15R5121126KudligiInfrastructureWater SupplySCP Water Purification plant at chikkajogihalli Tanda -500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.70 0.002.47Basement and cabin completed, Plant need to be erected.
41 BLY15R5121128KudligiInfrastructureWater SupplySCP Water Purification plant at Mahadevapur-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed Plant need to be erected.
42 BLY15R5121129KudligiInfrastructureWater SupplySCP Water Purification plant at Mahadevpur SC colony- Pre-fab hut (4.88m x 9.76m).KRIDL-H26/05/2016 2.60 2.470.00Under progress
43 BLY15R5121130KudligiInfrastructureWater SupplySCP Water Purification plant at Srikanthapur Tanda -500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.47Basement and cabin completed, Plant need to be erected.
44 BLY15R5121132KudligiInfrastructureWater SupplySCP Water Purification plant at Ammenhalli Tanda-500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.36Basement and cabin completed, Plant need to be erected.
45 BLY15R5121134KudligiInfrastructureWater SupplySCP Water Purification plant at chinnenhalli Tanda-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
46 BLY15R5121135KudligiInfrastructureWater SupplySCP Water Purification plant at chinnenhalli Tanda- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.00 
47 BLY15R5121136KudligiInfrastructureWater SupplySCP Water Purification plant at B.D.Gudda-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
48 BLY15R5121137KudligiInfrastructureWater SupplySCP Water Purification plant at B.D.Gudda - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
49 BLY15R5122138KudligiInfrastructureWater SupplyTSP Water Purification plant at Advisurwanahalli-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
50 BLY15R5122139KudligiInfrastructureWater SupplyTSP Water Purification plant at Advisurwanahalli- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
51 BLY15R5122140KudligiInfrastructureWater SupplyTSP Water Purification plant at geddalgatte - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
52 BLY15R5122141KudligiInfrastructureWater SupplyTSP Water Purification plant at geddalgatte - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
53 BLY15R5122142KudligiInfrastructureWater SupplyTSP Water Purification plant at Arjunachinnenahalli-500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.36Basement and cabin completed, Plant need to be erected.
54 BLY15R5122144KudligiInfrastructureWater SupplyTSP Water Purification plant at Kadekol- 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.47Basement and cabin completed, Plant need to be erected.
55 BLY15R5122146KudligiInfrastructureWater SupplyTSP Water Purification plant at A.Karnarhatti- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
56 BLY15R5122147KudligiInfrastructureWater SupplyTSP Water Purification plant at A.Karnarhatti- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54
57 BLY15R5122148KudligiInfrastructureWater SupplyTSP Water Purification plant at Jarmali- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
58 BLY15R5122149KudligiInfrastructureWater SupplyTSP Water Purification plant at Jarmali- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
59 BLY15R5122150KudligiInfrastructureWater SupplyTSP Water Purification plant at Kenchammanahalli- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
60 BLY15R5122151KudligiInfrastructureWater SupplyTSP Water Purification plant at Kenchammanahalli- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.00Under progress
61 BLY15R5122152KudligiInfrastructureWater SupplyTSP Water Purification plant at Ramdurga- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
62 BLY15R5122153KudligiInfrastructureWater SupplyTSP Water Purification plant at Ramdurga- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55 
63 BLY15R5122154KudligiInfrastructureWater SupplyTSP Water Purification plant at Kartikenhatti- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
64 BLY15R5122155KudligiInfrastructureWater SupplyTSP Water Purification plant at Kartikenhatti- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.53 
65 BLY15R5122156KudligiInfrastructureWater SupplyTSP Water Purification plant at Suttakaranahatti-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
66 BLY15R5122157KudligiInfrastructureWater SupplyTSP Water Purification plant at Suttakaranahatti- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.00Under progress
67 BLY15R5122158KudligiInfrastructureWater SupplyTSP Water Purification plant at Magapur- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
68 BLY15R5122159KudligiInfrastructureWater SupplyTSP Water Purification plant at Magapur- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55 
69 BLY15R5122160KudligiInfrastructureWater SupplyTSP Water Purification plant at Narsihagiri-500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
70 BLY15R5122161KudligiInfrastructureWater SupplyTSP Water Purification plant at Narsihagiri- Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.55 
71 BLY15R5122162KudligiInfrastructureWater SupplyTSP Water Purification plant at Ramsagarhatti- 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.36Basement and cabin completed, Plant need to be erected.
72 BLY15R5122164KudligiInfrastructureWater SupplyTSP Water Purification plant at chadrashekharpur-500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.47Basement and cabin completed, Plant need to be erected.
73 BLY15R5123096KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Hurlihal - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
74 BLY15R5123097KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Harakbavi - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.53 
75 BLY15R5123101KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Hyalya - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.00 
76 BLY15R5123103KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Bewur - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.00 
77 BLY15R5123105KudligiInfrastructureWater SupplyGENERALWater Purification Plant in APMC in Kottur - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.600.55
78 BLY15R5123106KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Rajiv Gandhi Nagar in Kottur - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.600.55
79 BLY15R5123107KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Kalapur - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
80 BLY15R5123108KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Siddapur waddarhatti cross - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.53 
81 BLY15R5123109KudligiInfrastructureWater SupplyGENERALWater Purification Plant in chikka Jogihalli - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54
82 BLY15R5123110KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Immadapur - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
83 BLY15R5123111KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Tulahalli - Pre-fab hut (4.88m x 9.76m)KRIDL-H26/05/2016 2.60 2.470.54 
84 BLY15R5123240KudligiInfrastructureWater SupplyGENERALWater Purification Plant in A.Dibbadahalli -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
85 BLY15R5123241KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Ranganathanhalli - 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 2.532.36Basement and cabin completed, Plant need to be erected.
86 BLY15R5123242KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Hurlihal -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
87 BLY15R5123243KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Harakbavi -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
88 BLY15R5123244KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Appenahalli- 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed, Plant need to be erected.
89 BLY15R5123245KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Tayakanahalli - 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS17/01/2018 8.74 2.531.01Basement and cabin completed, Plant need to be erected.
90 BLY15R5123246KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Amalapur - 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 0.002.36Basement and cabin completed, Plant need to be erected.
91 BLY15R5123247KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Hyalya - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed, Plant need to be erected.
92 BLY15R5123248KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Poojarhalli - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 6.22 2.531.01Basement completed, Plant need to be erected.
93 BLY15R5123249KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Bewur -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
94 BLY15R5123250KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Ayyanhalli - 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 2.532.47Basement and cabin completed, Plant need to be erected.
95 BLY15R5123251KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Taluka Hospital Kottur - 250 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.)RWS26/05/2016 4.22 0.000.00Basement completed, Plant need to be erected.
96 BLY15R5123252KudligiInfrastructureWater SupplyGENERALWater Purification Plant in APMC in Kotturu - 250 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 4.22 2.531.01Basement completed, Plant need to be erected.
97 BLY15R5123253KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Rajiv Gandhi Nagar in kottur R - 1000 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS17/01/2018 9.47 2.531.01Basement completed, Plant need to be erected.
98 BLY15R5123254KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Kalapur - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
99 BLY15R5123255KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Siddapur waddarhatti cross -500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
100 BLY15R5123256KudligiInfrastructureWater SupplyGENERALWater Purification Plant in chikka Jogihalli - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
101 BLY15R5123257KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Immadapur - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
102 BLY15R5123258KudligiInfrastructureWater SupplyGENERALWater Purification Plant in Tulahalli - 500 LPH RO PLANT(1.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water.) RWS03/03/2018 6.22 0.000.00Basement completed, Plant need to be erected.
103 BLY15R51239KudligiInfrastructureWater SupplyGENERALWater Purification Plant in T.Kallahalli - 500 LPH (1. Pre-fab hut (4.88m x 9.76m), 2.Concrete platform & Borewell,Electrification,Pipeline,Installation, Disposal of Waste water) RWS03/03/2018 8.74 2.532.36Basement and cabin completed, Plant need to be erected.
104 BLY15R6113032HadagaliInstitutionalSocialGeneralConst of M.Y.Ghorpade GP Building at BheerabbiNK06/04/2016 50.00 50.0031.78Ground floor Finishing stage FF Roof shettering completed
105 BLY15R7121217H.B.HalliInfrastructureWater SupplySCP Water Purification plant at Bovi colony- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.48Physically completed
106 BLY15R7121223H.B.HalliInfrastructureWater SupplySCP Water Purification plant at Warala - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.08Physically completed
107 BLY15R7121225H.B.HalliInfrastructureWater SupplySCP Water Purification plant at Kalla Halli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.53work completed
108 BLY15R7121227H.B.HalliInfrastructureWater SupplySCP Water Purification plant at Marbihal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.58Physically completed
109 BLY15R7121229H.B.HalliInfrastructureWater SupplySCP Water Purification plant at Nakkaral Tanda- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.53Physically Completed
110 BLY15R7122169H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Hosa Chinmalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.08Physically completed
111 BLY15R7122171H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Nanipur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.37Physically completed
112 BLY15R7122173H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Kanvi Nayakanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.07Physically completed
113 BLY15R7122175H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Adakanbavi- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.90Physically completed
114 BLY15R7122177H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Lokappanhola- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.09Physically completed
115 BLY15R7122179H.B.HalliInfrastructureWater SupplyTSP Water Purification plant at Byalal- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.87Physically completed
116 BLY15R7123183H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Vardapur- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.08Physically completed
117 BLY15R7123185H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Anka Samudra- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.39Physically completed
118 BLY15R7123187H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at B.G. Halli 2- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.09Physically completed
119 BLY15R7123189H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Shigenahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.98Physically completed
120 BLY15R7123193H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Hira Sobti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.00Physically Completed
121 BLY15R7123195H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Arlihalli Kuradagadi Housing Board Park- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.48Physically completed
122 BLY15R7123197H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Ram Rahim Nagar- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.48Physically completed
123 BLY15R7123199H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Uppinayakanhalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.97Physically completed
124 BLY15R7123201H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Vallabhapur - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.37Physically completed
125 BLY15R7123203H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Jalinagar- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.880.48Physically completed
126 BLY15R7123205H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Ramnagar Raitar Oni- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.69Physically completed
127 BLY15R7123207H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Hagari Bommanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.37Physically completed
128 BLY15R7123209H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Uppargatti- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 1.300.48Physically completed
129 BLY15R7123211H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Advi Anand Devanahalli- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.471.39Physically completed
130 BLY15R7123213H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Mehboobnagar - Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS26/05/2016 2.47 2.470.00Physically Completed
131 BLY15R7123215H.B.HalliInfrastructureWater SupplyGENERALWater Purification plant at Kudlgi circle- Concrete Platform/ Bore well & Electrification Pipeline, installation, Disposal of waste water.RWS16/02/2018 2.88 2.881.37Physically Completed
      TOTAL  898.17627.41236.37